Final turbine installed at SD wind farm

Email

SIOUX FALLS, S.D. (AP) -- The heavy lifting is done at the Crow Lake wind farm north of White Lake.

Basin Electric Power Cooperative says the last of 108 turbines was put in place this week. After some testing, the entire wind farm should be operational by late February.

Construction on the $363 million project began last October.