Road technique aims to handle heavy truck traffic

Email Sign up for Breaking News Alerts
news Dickinson, 58602
Dickinson North Dakota 1815 1st Street West 58602

WILLISTON -- A new technique being used in some North Dakota road repair projects aims to smooth out rough spots more quickly and with longer lasting results.

Advertisement
Advertisement

The North Dakota Department of Transportation is placing a concrete overlay on top of existing asphalt to better handle heavy truck traffic in the Oil Patch and elsewhere.

The technique, sometimes referred to as white topping, should eliminate the ruts that have been occurring on some northwest North Dakota highways, particularly at intersections, said Robert Seghetti, vice president for ACME Concrete Paving.

ACME, of Spokane, Wash., is using this technique in a road rehabilitation projects on U.S. Highway 2 north of Williston. ACME also is doing work near New Town.

"It should be a long-term solution to the rutting problem they have in North Dakota," Seghetti said.

In addition to improving load-carrying capacity and safety, the technique also is cheaper and can be completed more quickly than other resurfacing methods, said Clayton Schumaker, assistant materials and research engineering for the North Dakota Department of Transportation.

The NDDOT also used this technique in the Rugby and Hillsboro areas, Schumaker said.

The thickness of the concrete overlay ranges from 6 inches to 9 inches, Seghetti said. The concrete should require less maintenance and is projected to have a lifespan of 20 years or longer outside of Williston, he said. He estimated that the lifespan of the concrete within Williston would be 10 years or longer due to the stop-and-go traffic.

Williston City Commissioner Howard Klug said the time the technique saves is important for the community because of the heavy traffic congestion in the construction zones.

The concrete work on Highway 2 is expected to be complete during the first week in October and will open to the public later in the month, Seghetti said.

Advertisement
The Dickinson Press (701) 225-4205 customer support

Amy Dalrymple is a Forum News Service reporter stationed in the Oil Patch. She can be reached at adalrymple@forumcomm.com or (701) 580-6890.

Advertisement
Advertisement
randomness